<

VULCAN ENERGY RESOURCES LIMITED EQS-News: Vulcan Energy Resources Limited: Commissioning start at Lithium Extraction Optimisation Plant

Transparency directive : regulatory news

17/08/2023 10:01

EQS-News: Vulcan Energy Resources Limited / Key word(s): Miscellaneous
Vulcan Energy Resources Limited: Commissioning start at Lithium Extraction Optimisation Plant

17.08.2023 / 10:01 CET/CEST
The issuer is solely responsible for the content of this announcement.


Commissioning commences at Vulcan’s Lithium Extraction Optimisation Plant 

Major milestone for Vulcan

Significant step forward for the EU battery critical raw materials supply chain

 

Vulcan Energy Resources Limited (Vulcan; ASX: VUL, FSE: VUL, the Company), the renewable energy producer and carbon neutral lithium developer, has commenced commissioning at its Lithium Extraction Optimisation Plant (LEOP). 

 

Highlights: 

  • Vulcan has commenced commissioning of its Lithium Extraction Optimisation Plant (LEOP), for the purpose of extraction, purification, and concentration of lithium chloride from brine in the Upper Rhine Valley in Germany. This milestone represents a major step forward by Vulcan and its Zero Carbon Lithium™ Project. 
  • This also represents significant progress towards enabling domestic European supply chain independence for lithium as a critical raw material and enabling a more sustainable EV battery production industry in Europe. 
  • The commissioning phase for LEOP is expected to run until October, when first brine will be introduced into the plant for the lithium extraction process to begin. 
  • Vulcan commenced building its LEOP in 2022, designed as an optimisation, operational training and product qualification facility to enable commercial operational readiness for the end of 2025.
  • LEOP succeeds Vulcan’s pilot plant, which has successfully operated for 2.5 years, producing lithium chloride from Vulcan’s producing well sites.
  • To extract lithium from brine, Vulcan is using Adsorption-type DLE (“A-DLE”), which has been a commercially proven technology in the lithium industry since the 1990s. A-DLE is also beneficial in terms of low operating costs, greater time efficiency and a lower carbon footprint than legacy industry methods of lithium production. 
  • Vulcan will use its proprietary sorbent VULSORB® as part of the lithium extraction process. During the piloting phases, VULSORB® demonstrated higher performance and lower water consumption for lithium extraction compared with commercially available sorbents tested by the Company.
  • Once the lithium chloride is produced, it will be transported to Vulcan’s downstream Central Lithium Electrolyser Optimisation Plant (CLEOP) in Frankfurt-Höchst where the lithium chloride will be converted into lithium hydroxide, which will be tested by Vulcan’s lithium offtake partners, Stellantis, Volkswagen, Renault, Umicore and LG Energy Solution. 
  • Vulcan’s Phase One commercial operation is targeting 24,000 tonnes per annum of lithium hydroxide production, to supply its offtakers in Europe with carbon neutral, domestically sourced lithium. 

    

    

CEO, Cris Moreno, stated: "The commencement of the commissioning of our LEOP facility represents a significant milestone for us, as well as the entire European battery industry. By 2030, Europe is likely to face a significant lithium shortage, which could have serious implications for the European battery and automotive industries if domestic supplies are not realised. Vulcan is gearing up to be the first to produce lithium from Europe, for Europe, but also to be the first company worldwide to produce carbon neutral lithium. The start of the commissioning of our LEOP facility is a key step toward the implementation of Phase One of our Zero Carbon Lithium™ Project, and in enabling a secure and independent European supply chain for Lithium.

This is a great achievement of a determined team. Our pilot plants have already demonstrated the capability of A-DLE, a technology that has been commercially in use globally for decades, on our brines. With this determination, we will continue to advance in the coming months, driving the mobility transition in Europe, and serving as an inspiring example of what is possible, pioneering a carbon free future. “

 

 

About LEOP

Vulcan’s LEOP has been built to enable operational readiness when construction of the full commercial plant is completed, to reduce commercial ramp up time. LEOP has the same equipment that Vulcan’s commercial LEP will have, with adsorption columns at a 1:50 scale of the commercial unit, with a greater number of columns in the commercial plant. The LEOP will have the capacity to produce approximately 100 tonnes of lithium chloride solution per annum. 

The production volumes at LEOP will signify the first tonnes of lithium chloride concentrate domestically produced in Europe, and the first tonnes of lithium produced using the commercially proven method of Adsorption – type Direct Lithium Extraction (A-DLE) powered from renewable heat instead of gas.

fncls.ssp?fn=download2_file&code_str=5c652dd7197d2f458b0fa0e78d578b4b

Figure 1.  Vulcan's Lithium Extraction Optimisation Plant at Landau


fncls.ssp?fn=download2_file&code_str=b152859fdd1bf7604d9cfc3b7d655782

Figure 2. Crystalliser installation

 


fncls.ssp?fn=download2_file&code_str=586e56cb1c6162a369bf31af046977eb

Figure 3. Brine Conditioning System

 

About Vulcan

Founded in 2018, Vulcan’s unique Zero Carbon Lithium™ Project aims to decarbonise lithium production, through developing the world’s first net carbon neutral lithium business, with the co-production of renewable geothermal energy on a mass scale. By adapting existing technologies to efficiently extract lithium from geothermal brine, Vulcan aims to deliver a local source of sustainable lithium for Europe, built around a net zero carbon strategy with exclusion of fossil fuels. Already an operational renewable energy producer, Vulcan will also provide renewable electricity and heat to local communities.

Vulcan’s combined geothermal energy and lithium resource is the largest in Europe18F[1], with license areas focused on the Upper Rhine Valley, Germany. Strategically placed in the heart of the European electric vehicle market to decarbonise the supply chain, Vulcan is rapidly advancing the Zero Carbon Lithium™ Project to target timely market entry, with the ability to expand to meet the unprecedented demand that is building in the European markets. 

Guided by our Values of Integrity, Leadership, Future-focused and Sustainability, and united by a passion for the environment and leveraging scientific solutions, Vulcan has a unique, world-leading scientific and commercial team in the fields of lithium chemicals and geothermal renewable energy. Vulcan is committed to partnering with organisations that share its decarbonisation ambitions and has binding lithium offtake agreements with some of the largest cathode, battery, and automakers in the world.  As a motivated disruptor, Vulcan aims to leverage its multidisciplinary expert team, leading geothermal technology and position in the European EV supply chain to be a global leader in producing zero fossil fuel, net carbon neutral lithium while being nature positive. Vulcan aims to be the largest, most preferred, strategic supplier of lithium chemicals and renewable power and heating from Europe, for Europe; to empower a net zero carbon future.

 

Corporate Directory

 

Executive Chair                                         Dr. Francis Wedin

Managing Director and CEO                     Cris Moreno 

Deputy Chair                                             Gavin Rezos

Non-Executive Director                             Ranya Alkadamani

Non-Executive Director                             Annie Liu   

Non-Executive Director                             Dr. Heidi Grön

Non-Executive Director                             Josephine Bush

Non-Executive Director                             Dr. Günter Hilken

Non-Executive Director                             Mark Skelton

Executive Director, Germany                    Dr. Horst Kreuter

 

Company Secretary                                  Daniel Tydde

 

For and on behalf of the Board

Daniel Tydde | Company Secretary  

 

Media and Investor Relations contact 

Annabel Roedhammer, Director, Communications and Investor Relations and PR | aroedhammer@v-er.eu | +49 1511 410 1585

Please contact Vulcan’s Legal Counsel Germany, Dr Meinhard Grodde, for matters relating to the Frankfurt Stock Exchange listing on mgrodde@v-er.eu. 

 

 

Reporting calendar  

13 September 2023 Half Year Report 
27 October 2023 September Quarterly 
29 January 2024 December Quarterly Report
28 March 2024 Annual Report 

 

Disclaimer

Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which Vulcan operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement. No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside Vulcan’s control.

Vulcan does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of Vulcan, its Directors, employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement.

This announcement is not an offer, invitation or recommendation to subscribe for, or purchase securities by Vulcan. Nor does this announcement constitute investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used for the basis of making an investment decision. Investors should obtain their own advice before making any investment decision.

Vulcan has carried out a definitive feasibility study for Phase One of its Zero Carbon Lithium™ Project ('Project'), the results of which were announced to the ASX in the announcement "Zero Carbon Lithium Project Phase 1 DFS Results" dated 13 February 2023 ('DFS'), ('DFS Announcement'). This announcement may include certain information relating to the DFS.  The DFS is based on the material assumptions outlined in the DFS Announcement (see "Competent Person Statement" below).  While Vulcan considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct of that the range of outcomes indicated by the DFS will be achieved.  This announcement may also include certain information relating to Phase 2 of its Project, Vulcan has not yet carried out a definitive feasibility study for Phase Two of its Project. 

 

Competent Person Statement:

The information in this announcement that relates to Mineral Resources and Ore Reserves, and any Exploration Results and Production Targets, of Vulcan's Zero Carbon Lithium Project is extracted from the DFS Announcement, which is available to view on Vulcan's website at www.v-er.eu. Vulcan confirms that in respect of estimates of Mineral Resources and Ore Reserves, and any Exploration Results and Production Targets, included in this announcement:

 

  • it is not aware of any new information or data that materially affects the information included in the original market announcement, and that all material assumptions and technical parameters underpinning the estimates in the original market announcement continue to apply and have not materially changed; 
  • the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement; and
  • all material assumptions underpinning any production targets (and any forecast financial information derived from such production targets) included in this announcement continue to apply and have not materially changed. 

 

[1] According to public, JORC-compliant data. See Phase One DFS announcement, 13 February 2023.



17.08.2023 CET/CEST Dissemination of a Corporate News, transmitted by EQS News - a service of EQS Group AG.
The issuer is solely responsible for the content of this announcement.

The EQS Distribution Services include Regulatory Announcements, Financial/Corporate News and Press Releases.
Archive at www.eqs-news.com


Language: English
Company: Vulcan Energy Resources Limited
Level 2,267 St. Georges Terrace
6000 Perth
Australia
E-mail: dtydde@v-er.eu
Internet: www.v-er.eu
ISIN: AU0000066086
WKN: A2PV3A
Listed: Regulated Market in Frankfurt (Prime Standard); Regulated Unofficial Market in Berlin, Dusseldorf, Hamburg, Munich, Stuttgart, Tradegate Exchange
EQS News ID: 1705867

 
End of News EQS News Service

1705867  17.08.2023 CET/CEST

fncls.ssp?fn=show_t_gif&application_id=1705867&application_name=news&site_id=symex


Other stories

29/04/2024 11:07
29/04/2024 10:42
29/04/2024 11:08
28/04/2024 20:40
29/04/2024 06:38
29/04/2024 05:47
29/04/2024 07:00
29/04/2024 07:58
29/04/2024 06:00
29/04/2024 00:13
28/04/2024 13:46
28/04/2024 16:26
29/04/2024 01:00
28/04/2024 23:21
29/04/2024 09:18
29/04/2024 07:48
29/04/2024 01:02
29/04/2024 10:16
29/04/2024 00:32
29/04/2024 06:00
29/04/2024 05:00
28/04/2024 10:24
29/04/2024 08:00
29/04/2024 07:00
29/04/2024 02:17
29/04/2024 09:33
29/04/2024 09:19
29/04/2024 09:29
29/04/2024 10:06
29/04/2024 08:44
29/04/2024 08:08
28/04/2024 19:21
27/04/2024 20:48
28/04/2024 09:42
28/04/2024 12:18
28/04/2024 08:51
27/04/2024 13:26
29/04/2024 00:00