VULCAN ENERGY RESOURCES LIMITED EQS-News: Environmental and Social Impact Assessment completed for Phase One ZERO CARBON LITHIUM™ Project

Transparency directive : regulatory news

08/12/2023 09:43

EQS-News: Vulcan Energy Resources Limited / Key word(s): ESG/Study results
Environmental and Social Impact Assessment completed for Phase One ZERO CARBON LITHIUM™ Project

08.12.2023 / 09:43 CET/CEST
The issuer is solely responsible for the content of this announcement.


 Environmental and Social Impact Assessment completed  for Phase One ZERO CARBON LITHIUM™ Project

 

Vulcan Energy Resources Limited (Vulcan, ASX: VUL, FSE: VUL, the Company) announces that its Environmental and Social Impact Assessment (ESIA) for Phase One of its Zero Carbon Lithium™ Project (Project) has been completed by ERM. The ESIA is a prerequisite to the raising of sustainable or “green” debt finance and is an important third-party validation of the Project’s sustainability credentials. 

 

Vulcan is advancing Phase One of its ZERO CARBON LITHIUM™ Project: the first integrated project delivering renewable energy and lithium, from Europe for Europe. In doing so, Vulcan aims to:

  • Meet Europe’s battery electric vehicle critical raw material needs. 
  • Provide affordable, baseload renewable energy to local communities. 
  • Generate thousands of direct and indirect jobs linked to the energy transition, decarbonisation, and electrification of transport. 

 

Key outcomes of the ESIA report:

  • The environmental and social baseline, impact assessment, and cumulative impact assessment completed by ERM is in line with lenders’ requirements to ensure a level of environmental performance prior to the furnishing of debt finance, e.g. the International Finance Corporation (IFC) Performance Standards on Environmental and Social Sustainability, and the Equator Principles (EP4). 
  • ESIA notes there are multiple positive impacts of the Project, including renewable heating provision for local communities, and carbon neutral lithium production to decarbonise the lithium supply chain, in a world leading first for the industry. 
  • Other positive impacts noted in the ESIA included:
    • The creation of numerous energy transition jobs, as well as ongoing local innovation and research in green technologies; 
    • the Project is being developed entirely on industrial and farming land, with no material negative impact to the local environment, and farming activities continuing uninterrupted; and
    • there are no potential impacts of the Project classed as greater than “minor” post-mitigation; with most impacts classed as “insignificant”, during the construction, operation and decommissioning phases. 
  • An Environmental and Social Management Plan (ESMP) has been created in advance of construction start, in line with the ESIA recommendations and industry best practice. 
  • The ESIA and ESMP, key components towards the provision of green financing, will be integrated into Vulcan’s Phase One project-level debt and equity financing process, which has been initiated. 

 

Vulcan’s ESG Lead, Storm Taylor, commented: “The completion of the Environmental and Social Impact Assessment marks a significant milestone in the advancement of our Zero Carbon LithiumProject. The ESIA has validated the world-leading sustainability and social benefits our integrated renewable energy and lithium project will deliver to stakeholders. Uniquely, our Project has no potential impact classed as greater than “minor” post mitigation and has instead shown a range of positive impacts to both people and the planet. As a next step, we look forward to implementing the best practice Environmental and Social Management Plan (ESMP) developed, and to engaging with lenders on this matter during the Phase One financing process, which has been initiated.”      

fncls.ssp?fn=download2_file&code_str=b7f6cfb0f67e4f4823972775227f810d

                          Stakeholder engagement at the Zero Carbon Lithium Project.

 

 

About Vulcan

Founded in 2018, Vulcan’s unique Zero Carbon Lithium™ Project aims to decarbonise lithium production, through developing the world’s first net carbon neutral lithium business, with the co-production of renewable geothermal energy on a mass scale. By adapting existing technologies to efficiently extract lithium from geothermal brine, Vulcan aims to deliver a local source of sustainable lithium for Europe, built around a net zero carbon strategy with exclusion of fossil fuels. Already an operational renewable energy producer, Vulcan will also provide renewable electricity and heat to local communities. Vulcan’s combined geothermal energy and lithium resource is the largest in Europe[1], with license areas focused on the Upper Rhine Valley, Germany. Strategically placed in the heart of the European electric vehicle market to decarbonise the supply chain, Vulcan is rapidly advancing the Zero Carbon Lithium™ Project to target timely market entry, with the ability to expand to meet the unprecedented demand that is building in the European markets. Guided by our Values of Climate Champion, Determined and Inspiring, and united by a passion for the environment and leveraging scientific solutions, Vulcan has a unique, world-leading scientific and commercial team in the fields of lithium chemicals and geothermal renewable energy. Vulcan is committed to partnering with organisations that share its decarbonisation ambitions and has binding lithium offtake agreements with some of the largest cathode, battery, and automakers in the world. As a motivated disruptor, Vulcan aims to leverage its multidisciplinary expert team, leading geothermal technology and position in the European EV supply chain to be a global leader in producing zero fossil fuel, net carbon neutral lithium while being nature positive. Vulcan aims to be the largest, most preferred, strategic supplier of lithium chemicals and renewable power and heating from Europe, for Europe; to empower a net zero carbon future.

 

Corporate Directory

Executive Chair                                 Dr. Francis Wedin

Managing Director and CEO             Cris Moreno

Deputy Chair                                     Gavin Rezos

Non-Executive Director                     Ranya Alkadamani

Non-Executive Director                     Annie Liu   

Non-Executive Director                     Dr. Heidi Grön

Non-Executive Director                     Josephine Bush

Non-Executive Director                     Dr. Günter Hilken

Non-Executive Director                     Mark Skelton

Chief Representative GER               Dr. Horst Kreuter

Company Secretary                          Daniel Tydde

 

For and on behalf of the Board

Daniel Tydde | Company Secretary  


Media and Investor Relations contact

Australia: 

Annabel Roedhammer, Director Communications and Investor Relations | aroedhammer@v-er.eu | +49 (0) 1511 410 1585 

Please contact Vulcan’s Legal Counsel Germany, Dr Meinhard Grodde, for matters relating to the Frankfurt Stock Exchange listing on mgrodde@v-er.eu. 

 

Reporting calendar  

 

29 January 2024   December Quarterly 
28 March 2024   Annual Report 
27 April 2024   March Quarterly
12 September 2024     Half Year Report 

 

  

Disclaimer

Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which Vulcan operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forwardlooking statement. No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside Vulcan’s control.

Vulcan does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of Vulcan, its Directors, employees, advisors or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement.

This announcement is not an offer, invitation or recommendation to subscribe for, or purchase securities by Vulcan. Nor does this announcement constitute investment or financial product advice (nor tax, accounting or legal advice) and is not intended to be used for the basis of making an investment decision. Investors should obtain their own advice before making any investment decision.

Vulcan has carried out a definitive feasibility study (“DFS”) and bridging engineering study (“Bridging Study”) for Phase One of its Zero Carbon Lithium™ Project (“Project”), the results of which were announced to the ASX in the announcements "Zero Carbon Lithium Project Phase 1 DFS Results" dated 13 February 2023 (“DFS Announcement”) and “Positive Zero Carbon Lithium™ Project Bridging Study Results” on 16 November 2023 (“Bridging Study Announcement”). This announcement may include certain information relating to the DFS and the Bridging Study. The DFS and Bridging Study are based on the material assumptions and parameters outlined in their respective announcements. While Vulcan considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the Bridging Study or DFS will be achieved. This presentation may also include certain information relating to Phase Two of its Project, Vulcan has not yet carried out a definitive feasibility study for Phase Two of its Project. 

 

Competent Person Statement:

The information in this announcement that relates to estimates of Mineral Resources and Ore Reserves is extracted from the Bridging Study Announcement which is available to view on Vulcan's website at www.v-er.eu. Vulcan confirms that, in respect of the estimates of Mineral Resources and Ore Reserves included in this announcement: 

  1. it is not aware of any new information or data that materially affects the information included in the original market announcement, and that all material assumptions and technical parameters underpinning the estimates in the original market announcement continue to apply and have not materially changed; 
  2. the form and context in which the Competent Persons' findings are presented in this announcement have not been materially modified from the original market announcement; and 
  3. all material assumptions underpinning the production targets (and the forecast financial information derived from such production targets) included in this announcement continue to apply and have not materially changed.  

 

[1] According to public, JORC-compliant data. See Upgrade of Zero Carbon Lithium™ Project Resources, 29 September 2023



08.12.2023 CET/CEST Dissemination of a Corporate News, transmitted by EQS News - a service of EQS Group AG.
The issuer is solely responsible for the content of this announcement.

The EQS Distribution Services include Regulatory Announcements, Financial/Corporate News and Press Releases.
Archive at www.eqs-news.com


Language: English
Company: Vulcan Energy Resources Limited
Level 2,267 St. Georges Terrace
6000 Perth
Australia
E-mail: dtydde@v-er.eu
Internet: www.v-er.eu
ISIN: AU0000066086
WKN: A2PV3A
Listed: Regulated Market in Frankfurt (Prime Standard); Regulated Unofficial Market in Berlin, Dusseldorf, Hamburg, Munich, Stuttgart, Tradegate Exchange
EQS News ID: 1793015

 
End of News EQS News Service

1793015  08.12.2023 CET/CEST

fncls.ssp?fn=show_t_gif&application_id=1793015&application_name=news&site_id=symex


Other stories

29/04/2024 11:22
29/04/2024 11:08
29/04/2024 10:42
29/04/2024 10:27
29/04/2024 11:12
28/04/2024 20:00
29/04/2024 05:52
29/04/2024 07:00
29/04/2024 07:58
29/04/2024 09:16
29/04/2024 05:47
29/04/2024 01:00
28/04/2024 13:08
29/04/2024 10:46
29/04/2024 09:18
29/04/2024 11:48
29/04/2024 11:15
29/04/2024 06:11
29/04/2024 00:32
29/04/2024 06:00
29/04/2024 05:00
28/04/2024 10:24
29/04/2024 08:00
29/04/2024 09:00
29/04/2024 07:00
28/04/2024 23:17
29/04/2024 08:18
29/04/2024 10:49
29/04/2024 10:50
29/04/2024 00:15
28/04/2024 19:21
27/04/2024 21:03
27/04/2024 20:48
28/04/2024 09:42
28/04/2024 12:18
28/04/2024 08:51
27/04/2024 13:26
28/04/2024 04:52